City of Vancouver Construction Projects - Weekly Update

traffic cone
For the Week of April 17, 2017
 
City of Vancouver Projects

Phone: 360-487-7750 - Construction Services, Vancouver Public Works 

Please note: Project updates are posted on this page weekly. For all projects, the public is encouraged to go slow and exercise caution in construction zones. Be alert to workers, equipment, traffic changes and possible traffic delays. Unless noted otherwise, general construction hours for City of Vancouver projects are 7 a.m. to 5 p.m., Monday through Friday, but may continue as late as 8 p.m. and include weekends if needed. Weather and construction conditions may impact schedules. 

Sanitary Sewer Improvements – Portions of East McLoughlin Blvd, Grand Blvd, West 20th Street, NE 124th Ave and NE 22nd Street
Construction of sanitary improvements began during the week of March 20 at various locations throughout Vancouver, including portions of East McLoughlin Blvd, Grand Blvd, West 20th Street, NE 124th Ave and NE 22nd Street. Late afternoon and night work is planned for Wednesday, April 19, along Grand Blvd between East 5th and 6th streets. The entire project involves rehabilitating existing sanitary sewer mains and grouting numerous sanitary sewer manholes to prevent groundwater infiltration.

ADA Ramp Construction/Pavement Management Resurfacing
Construction began Wednesday, April 12, on a project to improve 96 pedestrian curb ramp corners to meet ADA accessibility requirements. The ramp construction will affect portions of six Vancouver neighborhoods, with completion targeted for early June in advance of asphalt resurfacing of about 20 lane miles of street this summer. The work is part of the City’s 2017 Pavement Management Program.

Ramp construction will begin in the Burton Ridge Neighborhood, where 24 street corners will get new ADA ramps. The following streets are involved: NE 92nd Avenue from NE 19th Street to NE 21st Street, NE 21st Street from NE 92nd Avenue to NE 98th Avenue, and NE 98th Avenue from NE 19th Street to NE 22nd Street. Other neighborhoods that will see some new ADA curb ramps are: Kevana Park, 4 corners; Cascade Southeast, 16 corners; Cascade Highlands, 40 corners; Mountain View, 6 corners; and Northwest, 6 corners.

The work will include pavement cutting, construction of the ADA ramps and curbs, and pavement striping and landscaping at some locations. In general, construction will take place between 8:30 a.m. and 5 p.m., Monday through Friday, but may run as late as 8 pm if needed.

Sanitary Sewer Improvements – NE 79th Street, NE 118th Avenue to NE 128th Avenue, and nearby residential streets
As part of the city’s Sewer Connection Incentive Program, construction crews are extending sanitary sewer lines in the Granada South neighborhood. The project will install approximately 14,500 feet of sanitary sewer main, including sewer laterals to property lines. In general, construction hours will be 7 a.m. to 5 p.m., Monday through Friday, with project completion expected in November.

NE 18th Street Improvement Project, Four Seasons Lane to NE 136th Ave
Construction began in late January on the next segment of the NE 18th Street Improvement Project, from Four Seasons Lane to NE 136th Avenue. The street is being upgraded to urban standards with additional travel lanes, an improved traffic signal system, street lights, and bike and pedestrian facilities. Installation of underground utilities is nearly complete on the south side of Northeast 18th Street, east of Northeast 125th Ave. Next steps include grading and placing rock for widening the south side of 18th Street; and utilities installation along the north side of the street, also east of 125th Avenue. In addition, Clark Public Utilities will be working in the area to relocate power poles as part of this project. Project completion is expected in early 2018. Work hours are generally 7 a.m. to 5 p.m., Monday through Friday but go as late as 8 p.m. if needed. www.cityofvancouver.us/18thStreet

Private Development Projects
For information regarding private development projects within the City of Vancouver, please visit this Community and Economic Development webpage


 

Elsewhere in Southwest Washington

Information about the projects listed below has been provided by other agencies and shared here for the convenience of Vancouver residents and businesses. Any project questions should be directed to the applicable agency.
 

Washington State Department of Transportation

Phone: 360-905-2000 | Southwest Region Construction Information & Advisory Webpage

Daytime traffic impacts typically take place between 6 a.m. and 6 p.m., and nighttime impacts between 6 p.m. and 6 a.m. Times may vary based on weather and other (construction-related) variables.

I-205 - Mill Plain Interchange to 18th Street Improvements:
Tuesday, April 18 to Friday, April 21: Both directions of Northeast 18th Street, between Northeast 112th Avenue and Northeast 107th Avenue, may alternate through a single-lane, daily, from 6 a.m. to 6 p.m., for sign installation and landscaping work.
 
I-5 - I-205 to North Fork Lewis River Bridge - Rehabilitate Pavement

Sunday, April 16 to the morning of Monday, April 17: Up to two lanes of southbound I-5, between Northwest La Center Road and the North Fork Lewis River Bridge will close overnight, from 9 p.m. to 6 a.m., for paving work.
Monday, April 17 to the morning of Friday, April 21: Up to two lanes of southbound I-5, between Northwest La Center Road and the Northeast 139th Street, will close nightly, from 7 p.m. to 6 a.m., for paving work.
Friday, April 21 to the morning of Saturday, April 22: Up to two lanes of southbound I-5, between Northwest La Center Road and Northeast 139th Street, will close overnight, from 9 p.m. to 8 a.m., for paving work.

I-5 - La Center Interchange
Monday, April 17 to the morning of Wednesday, April 19: All lanes of southbound I-5 near the La Center interchange, will be closed nightly, from 10 p.m. to 4 a.m., for bridge demolition work. Drivers will follow a signed detour.  
Monday, April 17 to the morning of Wednesday, April 19: The northbound I-5 off-ramp to La Center Road (Exit 16) will be closed nightly, from 7 p.m. to 6 a.m., for bridge demolition work.
Wednesday, April 19 to the morning of Friday, April 21: All lanes of northbound I-5 near the La Center interchange, will be closed nightly, from 10 p.m., to 4 a.m., for bridge demolition work. Drivers will follow a signed detour.
Wednesday, April 19 to the morning of Friday, April 21: The southbound I-5 off-ramp to La Center Road (exit 16) will be closed nightly, from 7 p.m. to 6 a.m., for bridge demolition work.
Beginning at 10 p.m., Tuesday, April 4 to the morning of Sunday, April 16: Drivers exiting southbound I-5 will be directed to use the roundabout at Northwest 31st Avenue on the west side of I-5 to points east of the highway. This detour will be in place around-the-clock.  

SR 502 – Widening from I-5 to Battle Ground
Monday, April 17 to Friday, April 21: A single-lane in either direction of SR 502, will close intermittently with flaggers, between I-5 to Battle Ground, daily, from 9 a.m. to 3 p.m., for roadway widening work.

NE 99th Street - SR 503 Intersection Improvements
Beginning Monday, April 17 until further notice: The eastbound direction of Northeast 99th Street from SR 503, will be closed around-the-clock, for intersection improvements. Drivers should watch for a signed detour and expect delays.
NOTE: All work is being done by Clark County.

I-5 - Gee Creek Rest Area - CLOSED
Monday, April 17 to Friday, April 21: The northbound Gee Creek Rest Area will be closed from 6 a.m., Monday, April 17, to 5 p.m., Friday, April 21, for annual maintenance work.

                                                                     --------------
Clark County

360-397-6118 | Clark County Road Projects Webpage

NE 119th Street, 72nd Avenue to 87th Avenue
Intermittent construction activity will occur as the project nears completion.  

A map showing alternate routes to avoid the construction area is available at: www.clark.wa.gov/public-works/ne-119th-street.

NE 99th Street and NE 117th Avenue/SR 503 intersection improvement
Work to improve NE 99th Street on both sides of the intersection will begin Monday, April 17. This construction will require closing NE 99th Street immediately east of the intersection for about two months. Drivers should follow detour signs or use an alternate route to bypass the closure. Information regarding the project and a detour map is posted at: www.clark.wa.gov/public-works/ne-99th-street-sr-503-intersection.

Construction also will require closing NE 99th Street immediately west of the intersection, starting on Monday, April 24, and lasting for about two weeks.

NE Etna Road – Cedar Creek Bridge replacement
NE Etna Road and Cedar Creek Bridge are open to traffic. Intermittent construction activity in the project area may result in periodic traffic delays over the next few weeks. 

NE 259th Street, NE 10th Avenue to NE Eighth Court – Utility work
A private contractor working for Clark Public Utilities has completed installing a water transmission line. The contractor is waiting for dry weather for final paving. The project should be complete by the end of April, depending on weather.

NE 50th Avenue (119th Street, NE 131st Street, NE 39th Avenue, NE Corbin Road, NE Salmon Creek Boulevard)
A private contractor working for Northwest Natural will install a new steel gas main on NE 50th Avenue, and down NE 131st Street to Salmon Creek Avenue. There will be periodic single-lane closures and brief traffic delays. All lanes will be open at night. Work will be completed by early summer. All questions can be directed to Nina Carlson, (Northwest Natural Gas, Marketing Office): 50-3721-2474or nina.carlson@nwnatural.com

NE 99th Street/LaLonde Drive, NE 25th Avenue to NE St. Johns Road – Traffic signal work
Construction will require intermittent lane closures during April and May. Drivers should expect some delays. This work will be done in advance of this summer’s asphalt overlay on NE 99th Street.