Preventive Surface Treatment Projects

2016 Neighborhoods Affected by Pavement Preservation

2016 Neighborhood Treatments

Pavement preservation work began in early July, and will continue throughout the summer. Many local neighborhood streets are part of the 2016 surface treatment work. The map above shows residential neighborhoods directly affected by pavement preservation work coming this summer - highlighted in orange.

2016 Pavement Preservation Project Streets & Schedules:

The following preservation work will occur at night, typically between the hours of 8 p.m. and 5 a.m., to minimize impacts to commuters. Please note that paving and surface treatments are highly dependent upon weather conditions, which can impact schedules.

Expected Work Dates Street Work Boundaries Neighborhood(s) Most Directly Impacted
July 22 & July 26-27 & Aug 1-2 NE 138th Ave NE 18th St to NE 28th St Landover-Sharmel
July 22 & July 26-27 & Aug 1-2 NE 18th St NE 138th Ave to NE 141st Ave Hearthwood
July 23 & July 26-29 NE 162nd Ave NE 39th St to NE Fourth Plain Blvd Burnt Bridge Creek
July 24 SE Cascade Park Dr SE Talton Ave to SE 162nd Ave Widwood, Lewis/Clark Woods, Bella Vista, Cascade South East, Fairway 164th
July 25 & July 28-29 SE 1st St SE 190th Ave to NE 202nd Ave/City Boundary Bennington
July 25 & Aug 1 SE 172nd Ave SE Mill Plain Blvd to SE 1st St Bennington
July 25 & Aug 4-5 SE Mill Plain Blvd SE 172nd Ave to SE 192nd Ave Bennington
July 26 & Aug 2-3 SE 192nd Ave SR-14 Ramp to SE 34th St Fisher’s Creek
July 26 SE 29th St SE 164th Ave to SE 176th Ave Fisher’s Landing East
July 31 & Aug 1 SE 164th Ave  SE Evergreen Hwy to SE 34th St Village at Fisher’s Landing & Columbia River

 

Preventive Surface Treatment Program Info

The preventive treatment projects alternate each year between the east and west sides of Vancouver. The focus for 2016 is east of Interstate 205.

Click here for the 2016 list of streets scheduled for preventive surface treatments

Click here to view the 2016 map of projects scheduled for preventive surface treatments.

Click here to view a handy reference guide with information about parking restrictions, watering restrictions and potential weather-related delays, along with general dos, don’ts and other tips.
 

Adjacent properties typically receive a door hanger notice about a week in advance and then again 24 hours in advance of the work. The 24-hour notice includes a list of streets in your area that are also receiving treatment. This can help as you plan where you can park and drive when your street is being resurfaced. Please note that schedules and locations shown here may be adjusted when needed due to weather and construction conditions.

There are a variety of preventive surface treatments used to extend the life of streets at a much lower cost than a standard asphalt overlay. These surface treatments include microsurfacing, slurry seal, chip seal and cape seal. The type of treatment depends upon several factors, such as current surface condition, carrying capacity and travel use.

The City of Vancouver has more than 1,800 lanes miles of streets. Each year, the City of Vancouver evaluates about half of those paved city streets and identifies areas where surface treatments could go the farthest in extending the life of the street and providing residents with better driving conditions. All paving applications are highly weather dependent. In case of rain, surface treatment work must be rescheduled.

Curb Ramp Improvements Prior to Surface Treatments

As a precursor to the surface treatment work, crews installed new intersection curb ramps or retrofitted existing curb ramps at various intersection locations to meet compliance requirements of the Americans with Disabilities Act. Click here to learn more about the City's annual curb ramp program.

What to Expect Prior to Paving Work?

In most cases, residences and businesses fronting impacted streets receive door hanger notices in advance of paving. Within construction zones, drivers are asked to be prepared for delays, watch for traffic changes, proceed slowly, and be alert to construction workers, bicyclists, pedestrians and other motorists. Regardless of the type, all paving applications are highly weather dependent.

Construction hours are typically from 7 a.m. to 5 p.m., Monday through Saturday, though work may continue as late as 8 p.m. if needed. All paving applications are highly weather dependent.In case of rain, paving must be postponed and rescheduled.

Microsurfacing

Microsurfacing begins as a coarse liquid application of dense-grade aggregate, asphalt emulsion, water and mineral fillers. The quick-setting emulsion allows traffic to begin using the new surface in a short time, as little as an hour depending upon conditions. As the product cures, the surface becomes smoother. The finished sealant forms a thin shell over the street's existing asphalt surface, extending the life of the underlying pavement. Micro-surfacing applications are generally applied on arterial and higher volume streets, and the quick-setting emulsion allows traffic to begin using the new surface in a short time, as little as an hour depending upon conditions. Microsurfacing provides more durability than a slurry seal.

The benefits of microsurfacing include:
- Reduced user delays
- Corrections to minor defects and ruts
- Surface improvements
- Greater durability than slurry seal for high traffic areas
- Increased skid resistance
- Cost-effective, long-lasting pavement preservation
 

Slurry Seal, Chip Seal & Cape Seal

Slurry Seal is a mixture of fine rock, asphalt, and water placed on the pavement about ¼-inch thick to protect the surface from sun and rain. Slurry seal applications are generally applied on lower volume local and residential streets.

Chip Seal is a layer of sprayed emulsified asphalt and then a layer of new rock. A chip seal treatment typically extends the life of a road by seven to 10 years and provides a new sealed surface at a fraction of the cost of a standard asphalt overlay.

Cape Seal is a surface treatment that begins with a chip seal and then combines a final slurry seal, or even a microsurface, application. This treatment can greatly extend the life of the roadway.

Questions?

Construction questions during summer street work:
Department of Public Works, Construction Services
360-487-7750
(7:30 a.m. to 4:30 p.m., Monday through Friday)